SB 1107, Chapter 1010, Statutes of 2026 · Wednesday 30 September 2026

School facilities: design-build: shade structures

Schools can bundle comparable shade-structure projects into one design-build solicitation through 2031.

The law gives school districts a streamlined option to procure multiple shade projects while retaining separate contracts for each site. It also caps certain accessibility upgrade costs for qualifying playground-integrated shade structures.

What the law does ​

  • Lets governing boards authorize bundled design-build solicitations for comparable shade projects at multiple sites through December 31, 2031, when the combined value exceeds $1 million and each project is no more than $10 million.
  • Requires every project selected through a bundled solicitation to have its own contract, value, scope, location, schedule, design, and construction.
  • Allows districts to award bundled contracts based on lowest bid or best value.
  • Caps required accessible-path-of-travel improvement costs at 20% of adjusted construction cost for qualifying pre-checked freestanding or playground-integrated shade projects.

Who it affects ​

  • School districts and their governing boards.
  • Students, staff, and visitors at school district, county office of education, charter school, and community college campuses.
  • Design-build contractors seeking school shade-structure work.

Context ​

The bundled-procurement authority expires for new contracts after December 31, 2031, though contracts entered by then may be completed later.